APPENDIX
Chapter A170, FEES
[HISTORY: Adopted by the Board of Supervisors of Shenandoah County at time of adoption of Code 9-23-1997 by Ord. No. 97-7 (see Ch. 1, General Provisions, Art. I). Amendments noted where applicable.]
BUILDING INSPECTIONS DEPARTMENT
[Amended 11-24-1998][Amended 8-11-2009]
|
Type of Fee |
Amount of Fee |
|
|
|
|
Commercial, Industrial, Institutional |
|
|
New construction, per square foot |
$0.20 |
|
Additions, per square foot |
$0.20 |
|
Alterations |
1% of cost |
|
Open storage structure (no floor plan) per sq. ft. |
$0.10 |
|
Minimum permit fee |
$75.00 |
|
Tennant fit-out |
$100.00 |
|
Change of Use Group |
$100.00 |
|
|
|
|
New construction, per square foot |
$0.10 |
|
Additions, per square foot |
$0.10 |
|
Alterations |
1% of cost |
|
Minimum permit fee |
$75.00 |
|
Miscellaneous Building Permit Fees |
|
|
Reroof, per building |
$75.00 |
|
Residing, per building |
$75.00 |
|
Swimming pool, per pool |
$100.00 |
|
Tents (over 900 sq. ft.) |
$75.00 |
|
Temporary construction trailer (plus electrical service fees) per trailer |
$75.00 |
|
Temporary sales trailer (single or double-wide units) (plus electrical service fees) per trailer |
$75.00 |
|
Towers, antennas, wind turbines, etc., per structure (plus sq. footage of equipment building and electrical fees) New communication equipment only |
$100.00 |
|
Alarm system (security system) |
$50.00 |
|
Special inspection |
$50.00 |
|
Reinspection fee |
$50.00 |
|
Signs (plus electrical fees ), per sign |
$50.00 |
|
Plans review fee (over 5000 sq. ft.;optional for additions and alterations) per sheet |
$5.00 |
|
Renewal of permit, per permit |
$50.00 |
|
Temporary certificate of occupancy (30 days) |
$100.00 |
|
Certificate of Occupancy (Existing building or structure) |
$100.00 |
|
Zoning permit |
$100.00 |
|
Appeal board application fee |
$125.00 |
|
Inspection prior to issuance of permit |
$50.00 |
|
Asbestos removal |
$50.00 |
|
Demolition |
$75.00 |
|
Zoning permit (commercial, industrial, etc.) |
$200.00 |
|
Electrical Permit Fees (all Use Groups except R-3 and R-4). Installations not referenced below will be charged 1% of the cost, not to exceed $750. "Cost" equals the fair market price on the electrical cost only. |
|
|
New installation (base fee) |
|
|
000-400 amp service |
$50.00 |
|
401-800 amp service |
$70.00 |
|
801-1200 amp service |
$80.00 |
|
1201and greater |
$100.00 |
|
Service upgrade |
Refer to new service fees |
|
(Add miscellaneous fees to base fee for total permit cost.) |
|
|
Miscellaneous fees |
|
|
Minimum permit fee |
$50.00 |
|
Receptacles, lights and switches, each |
$0.25 |
|
Circuits, each |
$1.00 |
|
Motors, each |
$10.00 |
|
Electric baseboard units, each |
$10.00 |
|
Electric water heater, each |
$15.00 |
|
Refrigeration/freezer units, each |
$15.00 |
|
Air conditioning and heating units, each |
$15.00 |
|
Transformers, each |
$15.00 |
|
Subpanels, each |
$25.00 |
|
Generators, each |
$25.00 |
|
Swimming pool (Includes all equipment for pool), per pool |
$100.00 |
|
Signs and billboards, per sign |
$50.00 |
|
Temporary pole service |
$30.00 |
|
Permanent pole service |
See new installation |
|
Outside pole lights (includes footer inspection) per pole |
$50.00 |
|
Fire alarm system |
$50.00 |
|
plus per pull station |
$ 3.00 |
|
Special inspection |
$50.00 |
|
Plug-in type appliances and equipment |
No charge |
|
Plumbing Permit Fees (all Use Groups except R-3 and R-4). Installations not referenced below will be charged 1% of the cost, not to exceed $750. "Cost" equals fair market price on the plumbing cost only. |
|
|
Plumbing permit (base fee for new construction and additions) |
|
|
One-story building |
$50.00 |
|
Two or more floors |
$75.00 |
|
Add miscellaneous fees to base fee for total permit cost |
|
|
Miscellaneous fees |
|
|
Minimum permit fee |
$50.00 |
|
Water lateral |
$50.00 |
|
Sewer lateral |
$50.00 |
|
Fixtures, appliances, equipment, devices or drains which connect to water supply or waste lines, each |
$40.00 |
|
Well (includes electrical permit and requires Health Department approval) |
$40.00 |
|
Special inspection |
$50.00 |
|
Sewer pump station (without building) each |
$50.00 |
|
Solar panesl (for heat, boilers, hot water, etc.) |
$50.00 |
|
Mechanical Permit Fees (all Use Groups except R-5). Installations not referenced below will be charged 1% of the cost, not to exceed $750. "Cost" equals fair market price or contract price on the mechanical cost only. |
|
|
Mechanical permit (new installations or replacements) |
|
|
Heating or cooling systems, each; includes |
$75.00 |
|
Heating or cooling units, each; includes |
$50.00 |
|
Gas service |
$40.00 |
|
Add per each connection |
$5.00 |
|
Tanks (install or remove) |
|
|
Above and below ground |
$50.00 |
|
Each additional tank |
$10.00 |
|
Commercial kitchen hood system |
|
|
Hood, each |
$50.00 |
|
Fire suppression system, each |
$50.00 |
|
Minimum permit fee |
$50.00 |
|
Fire suppression (NFPA 13, 13R, 13D) |
|
|
Base fee |
$100.00 |
|
Plus: |
|
|
Tanks and/or pumps |
$50.00 |
|
Sprinkler heads, each |
$0.50 |
|
Elevators, escalators, dumbwaiters, hoist, cranes |
$75.00 |
|
|
|
|
Building Permit Fee [Amended 8-11-2009] |
|
|
New dwellings |
$0.15 |
|
Minimum fee |
$100.00 |
|
Additions to dwellings |
$ 0.15 |
|
Minimum fee |
$75.00 |
|
Alterations to dwellings |
$ 0.15 |
|
Minimum fee |
$75.00 |
|
New accessory structures; |
$ 0.15 |
|
Minimum fee |
$50.00 |
|
Industrialized buildings; modular homes (sealed by DHCD): |
|
|
Third party inspection seal, minimum |
$100.00 |
|
Plus: |
|
|
Unfinished areas (exclude unfinished attics), per square foot |
$0.15 |
|
Finished areas (all habitable space), per square foot |
$0.15 |
|
Decks or porches, per square foot |
$0.15 |
|
Electrical service |
$50.00 |
|
Plumbing |
$40.00 |
|
Mechanical (when installed on-site and with active building permit, heating and/or air conditioning) |
$50.00 |
|
Gas service |
$40.00 |
|
Well |
$20.00 |
|
NOTE: No charge for unfinished attic space, crawlspaces, entry porches 9 square feet or less, nonstructural patios. |
|
|
Additions or alterations |
See residential building permit fees |
|
Manufactured home; mobile home (sealed by HUD): |
|
|
Manufactured home: transportable in one or more sections; is 8 body feet or more in width and 40 body feet or more in length in the traveling mode, or is 320 or more square feet when erected on site. |
|
|
Single-wide (one section): includes electrical service, plumbing connection |
$25.00 |
|
Double-wide (more than one section): includes electrical service, plumbing connection |
$100.00 |
|
Extra fees |
|
|
Gas service |
$40.00 |
|
Mechanical (When installed on-site and with active building permit, heating and/or air conditioning) |
$50.00 |
|
Well |
$20.00 |
|
Note: No charge for crawlspaces, entry porches 9 square feet or less, nonstructural patios. |
|
|
Additions or alterations |
See residential building permit fees |
|
Miscellaneous residential permit fees (Areas not covered by this fee schedule will be charged at 0.5% of the contract cost, not to exceed $250.) |
|
|
Demolition |
$50.00 |
|
Reroof (More than 25% of existing) |
$20.00 |
|
Residing (More than 25% of existing) |
$30.00 |
|
Swimming pool (Private use only) |
|
|
In-ground pool (add for electrical permit) |
$75.00 |
|
Above-ground pool (includes electrical permit) |
$45.00 |
|
Temporary certificate of occupancy (60 days) |
$50.00 |
|
Reinspection |
$50.00 |
|
Renewal of permit |
$50.00 |
|
Septic system application fee (after 11/19/1991) |
$50.00 |
|
Zoning residential permit |
|
|
New dwellings |
$100.00 |
|
Additions/accessory structures |
$35.00 |
|
Inspection prior to issuance of permit |
$50.00 |
|
Detached structures (under 150 square feet) |
$20.00 |
|
Residential towers, antennas, and wind turbines |
$50.00 |
|
Returned Checks "UCF" |
$35.00 |
|
Administrative fee, minimum |
$20.00 |
|
Hourly rate for research (FOIA) |
$30.00 |
|
Plan review fee (optional as needed) |
$50.00 |
|
Alarm system |
$40.00 |
|
Soil and erosion permit (less than 10,000 square feet) |
$30.00 |
|
Appeals board application fee |
$125.00 |
|
Inspection prior to issuance of permit |
$50.00 |
|
Electrical Permit Fees (Amended 8-11-2009) |
|
|
New installation |
|
|
100-200 amp service |
$50.00 |
|
201-400 amp service |
$70.00 |
|
401-600 amp service |
$80.00 |
|
Upgrade service only |
$50.00 |
|
Upgrade service with rewire |
Same as new installation |
|
Temporary service on pole (for construction) |
$30.00 |
|
Permanent service on pole |
Same as new installation |
|
Swimming pool (in-ground only) |
$50.00 |
|
Miscellaneous electrical work |
$30.00 |
|
Limited electrical work (with building permit) |
|
|
Base fee |
$30.00 |
|
Plus for each fixture, light, switch, receptacle |
$1.00 |
|
Plumbing Permit Fees (Amended 8-11-09) |
|
|
New construction (base fee) |
$40.00 |
|
Plus |
|
|
Each bathroom |
$10.00 |
|
Ground works (future use) |
$10.00 |
|
Water and/or sewer lateral (without new construction) |
$50.00 |
|
Well (includes electrical permit and requires Health Department approval) |
$40.00 |
|
With new construction |
$20.00 |
|
Addition to dwellings (See limited plumbing work.) |
Same as new construction |
|
Miscellaneous plumbing work |
$40.00 |
|
Limited plumbing work (with building permit) |
|
|
Base fee |
$10.00 |
|
Plus, for each plumbing fixture |
$5.00 |
|
More than 3 fixtures |
Same as new construction |
|
Replacing or repairing fixtures or electric water heaters |
No charge |
|
Mechanical Permit Fees (Amended 8-11-09) |
|
|
New installations (new construction, additions and alterations) |
|
|
All heating systems (electric, gas, fuel oil, wood, coal) |
|
|
Equipment and duct work, per system |
$50.00 |
|
Equipment only, per unit |
$40.00 |
|
Duct work only (with building permit) |
$30.00 |
|
Appliance installation with LPG or natural gas |
See gas service |
|
|
|
|
Gas service |
$40.00 |
|
Plus, for each unit or appliance add |
$5.00 |
|
Tanks |
|
|
Underground LP gas tanks (any size), per tank |
$35.00 |
|
Aboveground LP gas tanks (any siz), per tank |
$35.00 |
|
Underground fuel oil tanks (any size), per size |
$35.00 |
|
Aboveground fuel oil tanks (any siz), per tank |
$35.00 |
|
Remove underground tank (any size), per tank |
$35.00 |
|
Minimum permit (tank only) |
$35.00 |
|
Contractor's License Fee |
|
|
Single business license, per year |
$35.00 |
|
Multiple business license, per year |
$35.00 |
|
A license fee for a |
|
|
Toms Brook/Maurertown Sanitary District |
|
|
Health Department application after November 19, 1991 |
$50.00 |
|
|
|
|
Land Use Fee |
|
|
New applications |
|
|
Per acre |
|
|
Over 50 acres |
|
|
Before October 1 |
$0.20 |
|
October 2 to December 1 |
$0.40 |
|
50 acres or less |
|
|
By October 1 |
$10.00 |
|
October 2 to December 1 |
$20.00 |
|
Revalidation applications |
|
|
Per acre |
|
|
Over 50 acres |
|
|
Received by November 1 |
$0.20 |
|
November 2 to December 1 |
$0.40 |
|
50 acres or less |
|
|
By November 1 |
$10.00 |
|
November 2 to December 1 |
$20.00 |
|
An application fee shall accompany each application, except that no application shall be less than $10.00. No land use fees are refundable. |
|
|
|
|
|
Work release inmates for work release program |
|
|
Per week |
$60.00 |
|
Per day |
$12.00 |
|
Per diem (other jurisdictions) for housing and maintenance |
$45.00 |
|
Inmate doctor and dentist visits, each |
$15.00 |
|
Inmate prescription charges, each |
$5.00 |
|
Jail admittance processing fee |
$25.00 |
|
Peddling and soliciting |
|
|
Nonrefundable application fee |
$15.00 |
|
Additional fee |
$10.00 |
|
Criminal or traffic case in district or circuit court in which defendant is convicted of a violation of statute or ordinance, for funding of courthouse security personnel [Added 6-25-2002 by Ord. No. 02-8;6-26-07 by Ord. No.2007-13] |
$10.00 |
|
Processing fee for any individual admitted to a County, city or regional jail following conviction of any crime, including misdemeanors or violation of County ordinance or ordinance of any town located in the County, to defray cost of processing person into local or regional jail [Added 6-25-2002 by Ord. No. 02-9] |
$25.00 |
|
|
|
|
Regular tipping fee, per ton |
$36.00 |
|
Rough material tipping fee, per ton |
$52.50 |
|
Lightweight material tipping fee, per cubic yard |
$5.00 |
|
Separated recyclable tipping fee per ton |
$18.00 |
|
Car/light truck tires, each |
$1.25 |
|
Truck tires, each |
$3.00 |
|
Tractor/off-road tires, each |
$5.00 |
|
Mulch, per Bobcat scoop |
$4.00 |
|
Weighing, per vehicle |
$3.00 |
|
|
|
|
Fines |
|
|
Adult |
|
|
Books, magazines |
$0.10 per day; $3.90 maximum fine |
|
CDs, videos, DVDs |
$0.50 per day; $19.50 maxiumum fine |
|
Young adult and juvenile |
|
|
Books, magazines |
$0.05 per day; $1.95 maximum fine |
|
CDs, audios, audio kits |
$0.50 per day; $19.50 maximum fine |
|
Lost materials (material are considered LOST 39 weeks after they are checked out and not returned) |
$5.00 plus replacement cost of the material |
|
Library cards |
|
|
County residents with photo ID |
Free |
|
Out-of-County residents with library
cards from Handley Library or |
Free |
|
Other out-of-County residents |
$10.00 annually |
|
Photocopies, per page |
|
|
8.5 x 11 and 8.5 x 14 (b/w) |
$0.10 |
|
11 x 17 (b/w) |
$0.20 |
|
Printouts, per page |
|
|
8.5 x 11 and 8.5 x 14 (b/w) |
$0.10 |
|
8.5 x 11 and 8.5 x 14 (color) |
$0.50 |
|
Faxes |
|
|
Outgoing |
|
|
First page |
$2.00 |
|
Subsequent pages, each |
$0.50 |
|
Incoming, per page |
$0.50 |
|
|
|
|
Airport zoning appeals |
$100.00 |
|
Erosion and sediment control [Amended 10-26-2004 by Ord. No. 2004-14] |
|
|
Commercial/industrial developments |
$300.00 plus |
|
Subdivision developments |
$400.00 plus |
|
Other (private landowner disturbances) |
$100.00 plus |
|
Agreement in lieu of plan |
$30.00 |
|
Home occupations |
$50.00 |
|
Rezoning |
$300.00 plus |
|
Site plan review |
|
|
Nonresidential |
$500.00 plus |
|
Residential |
$300.00 plus |
|
Special use permits |
|
|
Level 2 home business |
$300.00 |
|
Other |
$400.00 |
|
Telecommunications towers |
$4,500.00 |
|
Subdivision approval |
|
|
Preliminary plat |
$150.00 plus |
|
Final plat |
$50.00 plus |
|
Administrative (single lot or boundary line adjustment) |
$50.00 |
|
Family or agricultural use only |
$35.00 |
|
Variances (appeals) to Board of Zoning Appeals |
$300.00 |
|
Zoning Ordinance text amendment |
$300.00 |
|
Zoning permit |
|
|
Residential accessory |
$20.00 |
|
Residential |
$35.00 |
|
Nonresidential |
$100.00 |
|
Inspection prior to issuance of a permit |
$50.00 |
|
|
|
|
Explosive storage permit |
$10.00 |
|
Blasting permit |
$10.00 |
|
Fireworks sales permit |
$30.00 |
|
Open burning permit |
$20.00 |
|
Fire Code appeals |
$200.00 |
|
False alarm fee |
$25.00 |
|
|
|
|
Rental Fees |
|
|
Ball fields (weekend tournaments), per field |
$25.00 |
|
Picnic shelters |
|
|
|
|
|
Weekdays |
$5.00 |
|
Weekends and holidays |
$10.00 |
|
Strasburg |
|
|
Per hour |
$5.00 |
|
All day |
$50.00 |
|
Refundable deposit |
$25.00 |
|
|
|
|
Half day (10:00 a.m. to 3:00 p.m./ 4:00 p.m. to dusk) |
$20.00 |
|
All day |
$40.00 |
|
|
|
|
Small shelter |
$35.00 |
|
Large shelter |
$50.00 |
|
|
|
|
Shelters |
$15.00 |
|
Refundable deposit - water use |
$10.00 |
|
New Market |
|
|
100-seat capacity |
|
|
11:00 a.m. to 4:00 p.m. |
$25.00 |
|
4:00 p.m. to 12:00 midnight |
$20.00 |
|
All day |
$45.00 |
|
75-seat capacity |
|
|
11:00 a.m. to 4:00 p.m. |
$20.00 |
|
4:00 p.m. to 12:00 midnight |
$15.00 |
|
All day |
$35.00 |
|
35-seat capacity |
|
|
11:00 a.m. to 4:00 p.m. |
$15.00 |
|
4:00 p.m. to 12:00 midnight |
$10.00 |
|
All day |
$25.00 |
|
Gazebo |
|
|
All day |
$25.00 |
|
|
|
|
Adoption fee, dogs and cats |
$15.00 |
|
Spay/neuter deposit, dogs |
$35.00 |
|
Spay/neuter deposit, cats |
$25.00 |
|
Claiming fee |
$10.00 plus |
|
Second claiming fee |
$15.00 plus |
|
|
|
|
Solicitor's license |
$25.00 |
|
Concealed handgun permit |
$35.00 |
|
Massage permit |
$40.00 |
|
Health club permit |
$50.00 |
|
Criminal/Traffic court cost |
$5.00 |
|
|
|
|
Home studies for custody and adoption Hourly rate set based on a time study done by Virginia Department of Social Services |
|
|
|
|
|
[Amended 12-10-2002 by Ord. No. 02-14; 6-8-2004 by Ord. No. 2004-07; 5-24-2005 by Ord. No. 2005-7; 5-9-2006 by Ord. No. 2006-2; 4-08-2008 by Ord No. 2008-3; 5-11-2010 by Ord. No. 2010-] |
|
|
A. Water and sewer billing. Rates for water and sewer service provided by Stoney Creek Sanitary District shall be billed on a bimonthly basis in arrears. |
|
|
B. Rates: |
|
|
Water |
|
|
0 to 3,000 gallons |
$38.00 minimum rate |
|
3,001 to 6000 gallons |
$4.00 per 1000 gallons |
|
Over 6,000 gallons |
$6.00 per 1,000 gallons |
|
Sewer |
|
|
0 to 3,000 gallons |
$50.00 minimum rate |
|
3,001 to 6,000 gallons |
$4.00 per 1,000 gallons |
|
Over 6,000 gallons |
$6.00 per 1,000 gallons |
|
|
|
|
Sewer flat rate (9,000 gallons) |
$80.00 billed bi-monthly |
|
|
|
|
C. Connection fees: |
|
|
Water |
|
|
0 to 3/4-inch service line |
$7,000 |
|
1-inch service line |
$12,600 |
|
11/2-inch service line |
$28,000 |
|
2-inch service line |
$49,700 |
|
|
|
|
Sewer |
|
|
0 to 3/4-inch service line |
$8,500 |
|
1-inch service line |
$15,300 |
|
11/2-inch service line |
$34,000 |
|
2-inch service line |
$60,350 |
|
|
|
|
D. Water and sewer connections larger than 2-inch: |
The charge for a connection larger than 2-inch shall
be calculated by using the Virginia Department of Health Waterworks
Regulation Design Criteria. Connection fees based on this criteria shall be
calculated by dividing the total number of design gallons by 250
(ERC-equivalent residential connection) and multiplying by the rate
established for a 3/4-inch service line. |
|
E. Criteria for payment of water and/or sewer connection fees. An actual connection sufficient to commence water and/or sewer service to a building, along with the obtaining of all necessary building permits, must be made within 6 months of payment of the connection fee. If such connection is not made within such time period, the party paying the fee may still connect to the system upon paying the fee then in effect at the time of actual connection. A credit of 100% will be given for the previously paid connection fee. |
|
|
|
|
|
F. Other fees: |
|
|
Voluntary disconnect due to planned vacancy |
Minimum six-month service fee |
|
Involuntary disconnect due to disaster where unit is uninhabitable |
No charge |
|
Nonpayment disconnect charge |
$25.00, minimum bimonthly service fees continue to accrue |
|
Account transfer |
$20.00 |
|
Renter security deposit |
|
|
Water and sewer |
$150.00 |
|
Water or sewer |
$75.00 |
|
|
|
|
Late fee |
10% of the current amount due after the 25th |
|
Returned check charge |
$30.00 |
|
After-hours service call |
$35.00 minimum |
|
Construction Inspection Fee |
$0.50/ft |
|
G. Effective date. Connection fees shall be effective on July 1, 2010. All other provisions of this ordinance shall be effective on July 1, 2010. |
|
|
|
|
|
[Amended 12-10-2002 by Ord. No. 02-13; 6-8-2004 by Ord. No. 2004-06; 5-9-2006 by ord. No. 2006-2; 4-08-2008 by Ord. No. 2008-2; 5-11-2010 by Ord. No. 2010-] |
|
|
A. Water and sewer billing. Rates for water and sewer service provided by Toms Brook/Maurertown Sanitary District shall be billed on a monthly basis in arrears. |
|
|
|
|
|
B. Rates: |
|
|
Water |
|
|
0 to 2000 gallons |
$25.00 minimum rate |
|
Over 2,001 gallons |
$5.50 per 1,000 gallons |
|
|
|
|
Sewer 0 to 2,000 gallons |
$23.00 minimum rate |
|
2,001 to 10,000 gallons |
$6.50 per 1,000 gallons |
|
Over 10,000 gallons |
$12.00 per 1,000 gallons |
|
|
|
|
Sewer flat rate (4,500 gallons) |
$39.25 billed monthly |
|
|
|
|
C. Connection fees: |
|
|
Water 0 to 3/4-inch service line |
$7,000 |
|
1-inch service line |
$12,600 |
|
11/2-inch service line |
$28,000 |
|
2-inch service line |
$49,700 |
|
*The cost for time and materials for making the connection are in addition to the fees listed above. |
|
|
Sewer 0 to 3/4-inch service line |
$8,500 |
|
1-inch service line |
$15,300 |
|
11/2-inch service line |
$34,000 |
|
2-inch service line |
$60,350 |
|
*The cost for time and materials for making the connection are in addition to the fees listed above. |
|
|
D. Water and sewer connections larger than 2-inch: |
The charge for a connection larger than 2-inch shall
be calculated by using the Virginia Department of Health Waterworks
Regulation Design Criteria. Connection fees based on this criteria shall be
calculated by dividing the total number of design gallons by 250
(ERC-equivalent residential connection) and multiplying by the rate
established for a 3/4-inch service line. |
|
|
|
|
E. Criteria for payment of water and/or sewer connection fees. An actual connection sufficient to commence water and/or sewer service to a building, along with the obtaining of all necessary building permits, must be made within 6 months of payment of the connection fee. If such connection is not made within such time period, the party paying the fee may still connect to the system upon paying the fee then in effect at the time of actual connection. A credit of 100% will be given for the previously paid connection fee. |
|
|
|
|
|
F. Other fees: |
|
|
Late fee |
10% of the current amount due after the 15th |
|
Nonpayment disconnect charge |
$25.00 |
|
Returned check |
$30.00 |
|
Service lock fee |
$25.00 |
|
Renters security deposit |
|
|
Water and sewer |
$150.00 |
|
Water or sewer |
$75.00 |
|
Account transfer |
$20.00 |
|
After-hours service call |
$35.00 minimum |
|
Septic tipping fee |
|
|
Toms Brook/Maurertown |
$70.00 per 1,000 gallons of truck capacity |
|
Construction Inspection Fee |
$0.50/ft |
|
|
|
|
G. . Effective date. Connection fees shall be effective on July 1, 2010. All other provisions of this ordinance shall be effective on July 1, 2010. |
|
|
|
|
|
Photocopies |
|
|
81/2 x 11 and 81/2 x 14 |
|
|
1 to 50 copies |
$0.25 per page |
|
51 to 100 copies |
$0.35 per page |
|
11 x 17 |
|
|
1 to 50 copies |
$0.35 per page |
|
51 to 100 copies |
$0.45 per page |